White Oak Kids Dental

A complex renovation kept moving through unexpected water damage, remediation, and repairs.

Project Overview

Cincinnati, Ohio

White Oak Kids Dental needed more than a finished space. The project required careful coordination between construction, dental equipment, vendors, and the details necessary to make the practice fully operational.

BuildWise served as the owner’s representative throughout the project, helping manage communication, coordinate vendors and equipment, oversee the schedule, and keep the many moving pieces aligned from construction through completion.

BuildWise Services

  • Owner’s Representation
  • Construction Management
  • Vendor & Equipment Coordination
  • Schedule Oversight
  • Project Communication
  • Move-In & Operational Support

The Challenge

Once construction began and the walls were opened, the team discovered significant water damage. The extent of the issue required professional remediation, additional repairs, and coordination with the practice’s insurance provider—all while protecting the surrounding space and preventing the problem from derailing the renovation.

BuildWise Role

BuildWise Solutions immediately coordinated the remediation process, working directly with the insurance provider while managing the necessary repairs. At the same time, the team managed the construction plan so work could continue safely in unaffected areas. This approach kept the larger project moving while ensuring the underlying damage was addressed thoroughly.

The Result

The unexpected damage was properly remediated, the necessary repairs were completed, and progress continued throughout the rest of the project. BuildWise turned what could have become a costly, project-stopping setback into a managed solution while protecting the practice, the renovation, and the client’s investment.

Planning a Dental, Healthcare, or Specialty Project?

BuildWise helps owners navigate construction with clarity from early planning through move-in.