Projects

Haverkos Family Orthodontics completed project exterior
Orthodontics

Haverkos Family Orthodontics

Each phase of this project considered the immediate needs of the business alongside the long-term potential of the property.

Planning extended beyond the orthodontic practice itself to accommodate future expansion, ensuring construction decisions didn't limit practice opportunities.

ZONING & APPROVALS
BuildWise Solutions navigated city and county requirements to keep the project moving toward construction.

BUDGET & FINANCING
Our team aligned construction decisions with financing and maintained budget oversight throughout the project.

VENDOR & EQUIPMENT COORDINATION
We worked to integrate contractors, dental vendors and equipment installation into one coordinated project schedule.

Pediatric Dental | Interior Renovation

White Oak Dental

An existing dental office was transformed into a pediatric practice designed around patient experience, clinical workflow and the specialized requirements of dental care. BuildWise Solutions coordinated construction, design, vendors and equipment to bring the finished space together while keeping the project moving toward opening.

CONSTRUCTION & DESIGN COORDINATION
BuildWise Solutions coordinated the contractor, design team and project decisions throughout the renovation, helping translate the plans into a functional pediatric dental practice.

VENDOR & EQUIPMENT COORDINATION
Dental equipment, cabinetry and specialized vendors had to align with construction, electrical and plumbing requirements. BuildWise Solutions integrated those vendors and installations into the overall project schedule.

SCHEDULE & PROJECT OVERSIGHT
We managed the moving pieces between contractors, vendors and equipment installation, identifying issues early and keeping work progressing toward completion.

0315 delhidental olson 5 (1)
Dental Practice | Expansion & Renovation

Delhi Dental

Expanding an operating dental practice meant construction had to work around the business, not the other way around. BuildWise Solutions coordinated a two-phase renovation and expansion that allowed Delhi Dental to continue serving patients while adding treatment space, upgrading the facility and navigating the unexpected challenges that came with construction.

PHASED CONSTRUCTION & OPERATIONS
The approximately six-month project was completed in two phases so the practice could remain operational. BuildWise Solutions coordinated construction activities, temporary front-desk needs and disruptive work around patient care and daily operations.

SCHEDULE & PROJECT COORDINATION
Demolition, heavy noise, contractors and construction activity had to be carefully scheduled around an active dental practice. BuildWise Solutions coordinated the moving pieces to keep both construction and the business progressing.

UNEXPECTED CONDITIONS & RESPONSE
When an equipment-related water event caused significant damage to the functioning side of the practice, BuildWise Solutions worked with the insurance process and coordinated the response and remediation while helping the practice remain operational.

You don't need to become a construction expert to build your business.

You need a partner who already is.